LAST NEWS

285091306_484096896804228_354006611160524809_n.jpg
19.jpg

The Handover

June 2022

The handover between Didier and Steve as Momentum project director is a major event and we have had the pleasure to celebrate it.

It is with emotion that we said goodbye to Didier Ohayon, we wish him the best for the future and we thank him for these years. 

As every great departure implies a great arrival, we all welcome Steve Suttie. We look forward to working with him and continuing to grow this project !

The Big Lift Happened

May 2022

A major milestone reached on ITER Worksite : The first Vacuum Vessel module of the machine has arrived inside the Tokamak PIT.
 All eyes were on this impressive crossing yesterday : heavy of 1380 T, this master piece of the fusion reactor has crossed all the building to reach is final place in the heart of the machine. This first section of the Vacuum Vessel is completed with thermal shield and two toroidal field coils.
 This long-planned operation has been successfully completed. Thanks to all the team who did an incredible and unforgettable job during all this process.

img_0281_sm.jpg
csm_1.jpg

Vacuum Vessel Sector #8
arrived from Korea

April 2022

A 440-tonne ITER vacuum vessel sector. It's the third procured by ITER Korea.

A barge brought the 440-tonne component across the inland sea of Berre to the start of the ITER road itinerary.

Following the ITER Itinerary, the convoy took four nights to reach the ITER site : it passed by 16 sleeping villages, many roundabouts and crossed the 30 bridges on the way.

The "Beating Heart" of the ITER Tokamak

February 2022

The central solenoid module is one of six more or less identical elements which, once assembled, will form the "beating heart" of the ITER Tokamak. The Central Solenoid has been dubbed "the most powerful magnet in the world''.

This magnet found its way into the Assembly Hall of ITER Worksite. Once finalized, it will be placed at the very center of the Tokamak PIT.

d.jpg
TCC2_META_Group_1_small.jpg

Second Vacuum Vessel Lift  

December 2021

On Monday 20th : the second vacuum vessel sector crossed the Assembly Hall and is now held in one of the two sub-sector assembly tools. The 440 tones heavy weight will be outfitted there with thermal shielding and two toroidal field coils. Another Tokamak Sector prepared and placed in its assembly tool where the silver coated thermal shield boards and 2 other magnets will be installed in the next months, before transfer to its final location where the vacuum vessel sectors chamber will be welded together. 

Start of TCC2 Site Activities

December 2021

On Thursday 17th : The worksite 2 was on the stage with the first support installed by TCC2. Indeed, a weld was performed and underlined the beginning of the TCC2 site activities. The TCC2 assembly contract was signed in December 2020 by the ITER Organization and the META SNC. This contract is one of the last major assembly and installation contracts planned for first-phase ITER assembly.  The TTC2 contract is for the installation of primary machine cooling water, test blanket module equipment, some vacuum pipework and vacuum vessel pressure suppression.

pf5_in_ass_hall_2_small.jpg
PF6_Crane_weight_1.jpg

Europe delivers poloidal field coil #5

July 2021

On Monday 26th, was delivered the Poloidal Field Coil #5, manufactured by Europe. One of the six ring-shaped coils required for the machine. It measures 17 metres in diameter and weights approximately 340 tonnes

First Poloidal Field Coil Lift

April 2021

On Wednesday 22nd was installed the Poloidal Field Coil #6. 9 temporary supports maintain the bottom cylinder. This 400-tonnes component—poloidal field coil #6 of 10 meters diameter is the first superconducting magnet to enter the Tokamak pit. Temporary supports will stay until the vacuum vessel is assembled and welded.

vvs6_inssat2_03.jpg
LCTS_Install_5b.jpg

First Vacuum Vessel Lift

April 2021

After several days of works preparation, tools set up, metrology with monitoring and tuning of the VV6 center of gravity, the lifting of the 440-tonnes Vacuum Vessel sector #6 and its positioning in the sector sub-assembly tool was done. Before the end of 2021, the 1,200-tonnes pre-assembly will be lowered into the pit, marking the first step in creating the Tokamak's toroidal chamber.

First thermal shield installed

January 2021

On January 24th, the ITER assembly and construction teams successfully inserted the cylindrical Lower Cryostat Thermal Shield into the Tokamak pit. Its silver-coated panels are designed to minimize the radiation heat load that will reach the magnets operating at 4.5 K.